This page explains what the rules and common practice call for. Every site is different, and what a survey or a filing needs at your facility is something we work out with you after we see it.

The trigger is an 8-hour time-weighted average (TWA) of 85 decibels (dBA), which is a 50% noise dose, measured without regard to any attenuation (noise reduction) from hearing protectors.

OSHA's noise standard calls this trigger the action level. Once any worker reaches it, you must have a hearing conservation program.

The exclusion of hearing protectors is the key to the whole standard. Handing out earplugs does not move you below the action level, and it cannot, because the action level is measured on the noise and not at the ear.

"Everyone wears plugs" does not take the place of the program. Hearing protectors are one of seven elements the standard requires once anyone reaches the action level.

The two trigger levels

Noise level (8-hour TWA) What it triggers Paragraph of the standard
Action level 85 dBA (50% dose) The full hearing conservation program (c)(1)
Permissible exposure limit (PEL) 90 dBA Feasible engineering controls (changes built into the job) or feasible administrative controls (changes to how the work is run) Table G-16, (b)(1)

The exchange rate is 5 decibels, meaning each added 5 decibels cuts the allowed time in half. That is OSHA's rate. Most of the rest of the world uses a 3 decibel exchange rate, which is why US and international noise studies of the same workplace come out with different numbers.

You do not have to work this out alone.Ron Fleming has done this work himself since 1993. We come to your plant, measure the noise, and tell you what you need and what you do not. See if we are the right fit. No cost.·More about noise surveys

When hearing protection alone can satisfy the standard

Table G-16 is OSHA's table of permissible noise exposures. Where workers are exposed above its limits, the noise standard requires feasible engineering or administrative controls.

The standard then adds a second step. If those controls fail to bring sound levels within the limits, personal protective equipment must be provided and used to bring sound levels within the table.

So under OSHA, hearing protection can be your means of compliance where those controls are not feasible.

The seven program elements

Once anyone reaches an 8-hour TWA of 85 dBA, you owe all of the following:

Element Paragraph of the standard What it means in practice
Noise monitoring (d) A monitoring program to identify who is at or above the action level. It is repeated under (d)(3) when a change in production, process, equipment or controls increases exposure. See below
Employee notification (e) Each worker who was monitored and is exposed at or above the action level must be notified of the results
Observation of monitoring (f) Workers or their representatives may observe the measurements being taken
Audiometric testing (g) A baseline audiogram and an annual audiogram, at no cost to the worker
Hearing protectors (i), (j) Made available at or above the action level, with a variety of suitable protectors to choose from. Use is mandatory in specified cases, with targets for the attenuation the protector must provide
Training (k) Annual. It covers the effects of noise, protector selection, fitting and care, and the purpose of audiometric testing
Recordkeeping (m) Keep noise exposure measurements for 2 years. Keep audiometric test records for as long as the worker is employed

When monitoring has to be repeated. The noise standard requires new monitoring whenever a change in production, process, equipment or controls increases noise exposure. The increase has to meet one of two conditions:

Both conditions turn on an increase. A change that leaves exposure where it was, or lowers it, does not by itself require a new survey, and the standard sets no annual schedule for one.

Note the record retention periods. Most chemical exposure records fall under a 30-year default that comes from OSHA's standard on access to exposure and medical records, and the noise periods are far shorter. The audiometric test record also outlasts the noise survey by decades, which becomes a problem when a claim arrives years later.

→ Access to exposure and medical records

Audiometric testing deadlines

This is where programs slip most often, because the clock starts on a hire date.

A baseline audiogram within 6 months of a worker's first exposure at or above the action level. The baseline is the reference against which later audiograms are compared.

Or within 12 months, where the employer uses a mobile test van to meet this requirement. That extra time comes with a condition: where the baseline is delayed beyond 6 months, the worker must wear hearing protectors for any period past 6 months after first exposure, until the baseline audiogram is done.

Annually after that, for every worker in the program.

The mobile van route is common and fully permitted. What gets missed is the hearing protector condition attached to it, which sits in the timing paragraph of the standard and not in the hearing protector paragraph.

→ Standard threshold shift (STS): when an audiogram shows a drop in hearing

What a complete program looks like on paper

That makes seven items. Two gaps turn up most often: the records showing workers were notified of their results, and the written comparison against baseline. Both sit between the audiometric testing provider and the employer, and each side tends to assume the other holds them.

When you may not need this

If nobody in your plant reaches an 8-hour TWA of 85 dBA, none of the hearing conservation requirements in OSHA's noise standard apply. A written survey is what demonstrates it.

A floor that sounds loud on a walkthrough is not the test, because the sound level at one moment is not the dose over a shift. An 88 dBA area that a worker occupies all day produces a higher dose than a 100 dBA machine run for 45 minutes. The only way to know is to measure the right thing on the right people.

→ How many employees to sample for noise

What we do

Our part is the noise survey. Workers wear noise dosimeters set to count sound from 80 dBA up, and a sound survey groups workers by how much of the shift each one spends in the noise, not by machine.

The report should give each worker's 8-hour TWA and dose, and compare both against the action level and the PEL. A useful report also states which of the seven elements each result triggers, and by when.

We do not perform audiometric testing, train workers or manage the program. Those elements are outside the four fields we work in.

→ Noise surveys · → Personal noise dosimetry · → Hearing protector selection · → Octave band analysis

Plan a noise survey to see who belongs in your program

Ron Fleming has done this work himself since 1993. You talk directly to the person who does the job. No account managers. No call center. Our prices are well below the competition. Tell us what is going on and we will send a written scope of work and a price, at no cost.

Talk with us. No cost.

References

The regulations and standards behind this page, with links to the official text, so you can check the source yourself.